Granite Falls Boulevard Extension

 

This $2.02 million project will construct a quarter-mile extension of Granite Falls Boulevard between Rogers Road and Grand Rock Way. There will be one lane of travel in each direction, and sidewalks will be installed on both sides of the road.

Project designs include bicycle lanes for each side of the new roadway. The existing portion of Granite Falls Boulevard between Rogers Road and West Young Street will be re-striped to remove the center turn lane and add bicycle lanes. This plan is in keeping with the Town’s adopted Bicycle Plan.

At the completion of the project, a traffic signal will be installed at the intersection of Rogers Road and Granite Falls Boulevard.

This additional road segment and traffic signal will improve traffic circulation in the immediate area. This project is also part of a long-term plan to improve road connectivity within the Town by extending Granite Falls Boulevard from West Young Street to Burlington Mills Road.

IMPACTS

Since the majority of the project is occurring on new right-of-way, minimal impact is expected to traffic on Rogers Road. These impacts are most likely to occur during utility work and as the two roadways are connected.

The contractor’s workdays will begin at 7am. To keep the project on schedule, expect crews on site Monday through Saturday, weather permitting.

The site contains several large rock formations, and blasting will be necessary as part of this project. Notice will be provided to residents and businesses in immediately surrounding structures.

SCHEDULE

Construction on the site will begin Monday, January 21. The project is expected to be complete by late June. Weather delays may extend the time needed to complete the project.

 

Project Updates: 
Granite Falls Boulevard February Update
Friday, February 8, 2019

Blasting at the site will occur during the weeks of February 11th and February 18th. Work has already begun clearing the land and constructing stormwater basins. The coming weeks will consist of blasting activities and the beginning of utility installation.

UPDATED February 22: Due to additional rock discovered on the site, blasting will continue during the weeks of February 25th and March 5th.

Granite Falls Boulevard March Update
Thursday, March 7, 2019

Most of the blasting work at the site has completed, but some additional blasting may be required in the coming weeks. A rock crusher will be delivered next week to repurpose the excavated rock as fill-in for the low areas of the site. Grading is also expected to begin this month. Work continues on the two stormwater basins and utility installation.