Completed: Jun 1, 2020
Public Works Facility
Identify Land
May, 2020
Feasibility Study
June, 2020
Purchase Property
Completed: May 26, 2021
May, 2020
Start Facility Design
July, 2021
Annexation/Zoning Neighborhood Meeting & 30% Design/Cost Review with Town Board
January 2022
Annexation/Zoning Approval
February 2022
Final Design & Budget Established
April 2022
Construction Begins
Fall 2022

The purpose of this project is to build a Public Works Facility that will house the department with room to grow as the Town grows in the future.
This project involves the purchase of 15.25 acres along East Young Street near 401 bypass. This project includes several stages:
- Identify parcel of land
- Feasibility Study of preferred property
- Concept drawing of facility
- Purchase property
- Facility Design
- Construction of facility
Documents
Site Layout & Budget