Traffic Impact Analysis

**Contact the Planning Department with questions - planning@rolesvillenc.gov or 919-554-6517 .  Thank you!

 

  • Developer conducts an ITE trip generation exercise to determine if the project hits the thresholds contained in LDO Section 8.
  • Developer contacts Planning Director to hold a Scoping meeting.
  • The Town assigns the TIA work to one of two on-call consultants – Stantec OR DRMP. 
  • Scoping meeting is held – Developer, TIA consultant, Planning Director.
  • TIA consultant produces a Cost Estimate based on the Scope of work and presents that to the Town and Developer.
  • Developer agrees to the Cost Estimate.
  • An Invoice is generated by Planning Director, sent to Developer.
  • Developer pays Invoice.
  • TIA Consultant begins the study. Timeframe is anywhere from 1-3 months typically, but varies.
    • Traffic Counts should be taken during active public/private school operations; traffic counts should not be taken during late May, June, July, August, late November, late December, and the WCPSS traditional calendar 'spring break' period.
  • Draft study presented to Town and Developer.  If there is an associated Rezoning Map Amendment involved, the PLanning Board meeting may be conducted utilizing Draft.
  • Draft study is sent to NCDOT Congestion Management for comment.
  • Revisions occur as necessary from all sides.
  • Final TIA is produced.
  • When Final TIA is produced, if there is an associated Rezoning Map Amendment involved it can move forward to the Board of Commissioners/legislative hearing.