The Point

 

Application
Completed: Dec 18, 2018
Winter 2018
Neighborhood Meeting
Completed: May 8, 2019
Spring 2019
Second Neighborhood Meeting
Completed: May 22, 2019
Spring 2019
Third Neighborhood Meeting
Completed: Jun 20, 2019
Summer 2019
Town Board Public Hearing
Completed: Aug 6, 2019
Summer 2019
Town Board Public Hearing (cont'd)
Completed: Aug 20, 2019
Summer 2019
Preliminary Subdivision Plat Submittal
Completed: Jan 28, 2020
January 28, 2020
TRC Review of Preliminary Subdivision plat
Completed: Sep 15, 2020
Winter 2020
Planning Board Review of Preliminary Subdivision Plat
Completed: Sep 28, 2020
Spring 2020
Town Board Review of Preliminary Subdivision Plat
Completed: Oct 6, 2020
Late Spring 2020
Town Board - Annexation Approved
Completed: May 4, 2021
Spring 2021
Site Plan for Townhomes Approved
Completed: Feb 1, 2022
Winter 2022
Site Plan for (South) Amenity Center Submitted
Completed: Apr 1, 2022
Spring 2022
Town Board Review of Preliminary Subdivision Plat for Point North Ph 11-13
Completed: Sep 6, 2022
September 2022
Construction Drawings Phases 11-13
Completed: Nov 2, 2022
November 2022
Revision to Approved CD 20-06
Completed: Nov 17, 2022
November 2022
MA 09-02 - APPROVED - Shearon Byrun Williams Property

Circa 2008 and 2009, an earlier iteration of the Point project was proposed and reviewed by the Town.

On August 3, 2009, the Town Board conducted an Evidentiary Quasi-Judicial hearing on MA 09-02, a request to rezone 339 acres from R-1 to R-PUD and develop 650 single family detached dwelling units and 250 single family townhome units, 10.82 acres of retail/office space, 81 acres of open space (30 acres usable), greenway/bike trails, and required infrastructure. At this meeting, the Board voted unanimously to Approve the rezoning portion, and to table the Special Use Permit (which included the PUD Master Plan and Conditions of Approval) to the September 8, 2009 meeting.

On September 8, 2009, The Town Board continued the Evidentiary Quasi-Judicial hearing, and discussed changes to the proposed Conditions of approval. The Board then unanimously approved the Special Use Permit, with a change to Condition #11. 

The ORDER of Approval document was approved by the Town Board on __date tbd__ as Consent Agenda Item __tbd__, and this document was recorded on __date tbd__ as BK ___xxx__/PG__xxx__. 

SUP 18-09 (Approved) - Special Use Permit

A Special Use Permit request to adopt a new PUD master plan for residential, open space, and commercial uses. The property is 316.38 acres and is split by Louisburg Rd. (US 401 Bypass). It is zoned the Residential and Planned Unit Development [R&PUD] zoning district under the Unified Development Ordinance (UDO).  Approval occurred during the Fall of 2019.  The ORDER of Approval document was approved by the Town Board on __date tbd__ as Consent Agenda Item __tbd__, and this document was recorded on __date tbd__ as BK ___xxx__/PG__xxx__. 

PR 20-01 - APPROVED - The Point SOUTH - Phase 1-10, & 14.   Preliminary Subdivision Plat for Phases 1-10, 14, proposing 485 single-family detached lots/319 townhome lots on 264.27 acres. On 2020-09-28, the Planning Board  voted unanimously to Recommend Approval with Conditions to the Town Board.  On 2020-10-06, the Town Board of Commissioners  voted unanimously to Approve with Conditions Item C.3.  The ORDER of Approval document was approved by the Town Board on __date tbd__ as Consent Agenda Item __tbd__, and this document was recorded on __date tbd__ as BK ___xxx__/PG__xxx__. 

ANX 20-05 - APPROVED - Annexation of 296.634 acres was Approved by the Town Board of Commissioners on May 4, 2021 via Ordinance 2021-O-04. Recorded on 05/24/2021 - see Recorded Document Bk018516/Pg00816.

SP 20-04 - APPROVED - Site Plan for 3 areas of Townhomes within the Point South project.  319 Townhomes are proposed in 3 separate areas of The Point South.  Agenda Item C.5 was approved unanimously by the Town Board on 2/1/2022 with an Evidentiary Quasi-Judicial Hearing.  The ORDER of Approval document was approved by the Town Board on __date tbd__ as Consent Agenda Item __tbd__, and this document was recorded on __date tbd__ as BK ___xxx__/PG__xxx__. 

PR 20-06 - APPROVED - Preliminary Subdivision Plat for Point NORTH Phase 11-13 - Preliminary Subdivision Plat subdividing 45.39 acres to create 94 SFD residential lots and 3 open space lots. Application was reviewed by the Planning Board on July 25, 2022, and was recommended to conduct a Quasi-judicial hearing before the Town Board.  On September 6, 2022, the Town Board of Commissioners conducted a Quasi-Judicial hearing and voted 3-2 to Approve the application, with conditions that 1.) the Applicant reimburse the Town for installation cost of 2 Stops Signs on Virginia Water Drive at Genovesa Drive, and 2.) Applicant provide $7,500 to Town for pedestrian safety improvements on Genovesa Drive as the Town determines appropriate. 

The ORDER of Approval document was approved by the Town Board on __TBD__  as Consent Agenda Item _TBD__, and this document was recorded on __date tbd__ as BK ___xxx__/PG__xxx__.

CD 20-06 - APPROVED - Construction Drawings for Point South, Phases 1, 2, 6, & 9.  This is referred to as "Package 1".  Approved & Signed by City of Raleigh (no date), Wake County (04/22/2022), and Town Planning Director (04/25/2022) - Approved date to be 04/25/2022.  See uploaded fully signed plan set broke into 5 parts.


CD 20-08 - Construction Drawings for Point South, Phases 3,4,5,7, & 10.  This is referred to as "Package 2". 

- 1st Submittal - rcvd 07-28-2021;  Comments published 02-11-2022. 

- 2nd Submittal - rcvd 02-25-2022- 9 PDF's; the CD plans are broken into 5 parts due to File size restrictions; on TRC-STAFF review 3/2/2022; Comments published 3/22/2022.

- 3rd Submittal - rcvd 04-15-2022- 7 PDF's; the CD plans are broken into 5 parts due to File size restrictions; on TRC-STAFF review 4/20/2022; Comments published 5/11/2022.

- 4th Submittal - rcvd 06-02-2022; 11 PDF's, CD plans broken into 7 parts; on TRC-STAFF review 06/07/2022; Comments published 06/21/2022

CD 22-03 - Harris Creek Interceptor Construction Drawings - Off-site sewer improvements  along Harris Creek on multiple properties in Town's Extraterritorial Jurisdiction (ETJ). Project is related to The Point project.  Proposes 418 LF of 18" sewer line, 3,469 LF of 24" sewer line, and 13 manholes.  See this City of Raleigh Utility Department webpage about the project.

- 1st Submittal -- Received 11-09-2021. Not officially reviewed by TOR TRC Staff.  

- 2nd Submittal -- Received 06-08-22, on review 06-27-22; Comments published 07-08-2022.

- 3rd Submittal - Received 09-23-2022, on review 09-30-22, Comments published 10/12/2022.  There are no further Comments, and Applicant is to attain signatures on Signature set of plans.

SP 22-04 - Site Plan for an Amenity Center in the South portion of development, on proposed lot OS-17 (Amenity Area) within Phase 1 from PR 20-01 approved by Town Board on 10/6/2020.  Property is zoned R&PUD under the Unified Development Ordinance, and per Section 6.2.7.(c)(5.) and (6.), a detailed Site Plan is required that is reviewed by the Planning Board and approved by the Town Board within the process of a Quasi-Judicial Evidentiary hearing. 

- 1st Submittal received 4/1/2022; on TRC-STAFF review 4/6/2022; Comments published 05/03/2022. 

- 2nd Submittal received 7/15/22; on TRC-STAFF Review 7/21/2022; Comment published 08/04/2022.

- 3rd Submittal received 09/30/2022; on TRC-STAFF Review October Cycle (10/5/22-11/2/22). Comments published 11/03/2022.

CD 22-05 - Point North Phases 11, 12, 13 - Construction Drawings plans pursuant to PR 20-06 for Phases 11, 12, 13 located on the 'north' side of NC Highway 401 Bypass, west of E. Young Street. Plans for constructing infrastructure improvements on 45.39 acres to create 94 Single-Family Detached residential lots and 3 open space lots and all development of associated public streets, utilities, and stormwater management.   

- 1st Submittal received 10/28/2022; on TRC-STAFF review 11/03/2022; Comments to be published by/on 12/5/2022.

CD 20-06 REVISION - __________ - Construction Drawings for Point South, Phases 1, 2, 6, & 9.  This is referred to as "Package 1".   This is a revision to the original application, approved on 04/25/2022, to include a new SCM "P" and associated storm drainage and erosion control measures. The area is near the planned Amenity Center (see SP 22-04).

- 1st Submittal (complete) received 11/17/2022; on TRC-STAFF review 11/21/2022; Comments to be published by/on 12/6/2022.

Developer

Ashton Residential Raleigh LLC
900 Ridgefield Drive, Suite 335
Raleigh, NC 27609

Engineer

McAdams
2905 Meridian Parkway
Durham, NC 27713

Documents

PR 20-06 - The Point NORTH - Phases 11-13 - Town Board Meeting
CD 20-08 -- Point SOUTH - Package 2_Ph 3, 4, 5, 7, & 10 - 1st Submittal
CD 20-08 -- Point SOUTH - Package 2_Ph 3, 4, 5, 7, & 10 - 2nd Submittal
CD 20-08 -- Point SOUTH - Package 2_Ph 3, 4, 5, 7, & 10 - 4th Submittal
CD 22-03 - Harris Creek Sewer improvements - 1st Submittal

Project Updates

Town Board of Commissioners Mtg on September 6, 2022
Friday, August 26, 2022

Preliminary Subdivision Plat PR 20-06 for Point North Phases 11, 12, 13 will be presented for a Quasi-Judicial Hearing before the Town Board of Commissioners at their regularly scheduled meeting on Tuesday, September 6, 2022, beginning at 7:00 PM.

For agenda and packet/information, please go to https://www.rolesvillenc.gov/agendas-minutes - information will be posted on August 31st/September 1st, 2022.

Planning Board Meeting July 25, 2022
Friday, July 8, 2022

PR 20-06 - Preliminary Subdivision Plat for Point NORTH Phases 11-13 is slated to be on the agenda for this Planning Board meeting for review and recommendation prior to the application being scheduled for an Evidentiary Quasi-Judicial public hearing before the Town Board of Commissioners (date TBD).

Town Board of Commissioners Meeting
Tuesday, February 1, 2022

SP 20-04, a Site Plan application for the areas of Townhomes within The Point PUD Master Plan (approved SUP 18-09). An Evidentiary Quasi-Judicial hearing will be held.

SUP 18-09 Approved
Wednesday, August 21, 2019

On August 20, 2019, the Town Board of Commissioners voted 3-2 in favor of approving SUP 18-09. The approval marks the adoption of the master plan for the The Point subdivision. Now, the petitioners must submit detailed site plans for all multi-family sections of the development.

Public Hearing Continued
Wednesday, August 7, 2019

On August 6, 2019, the Town Board of Commissioners voted to continue the public hearing for SUP 18-09. There will be a second meeting on August 20 at 6:00 p.m. to resume the discussion of the proposal.

Public Hearing Scheduled
Tuesday, July 23, 2019

The Town Board will hold a public hearing for SUP 18-09 on August 6, 2019 at 7:00 p.m. The meeting will be in the Board Chambers at Town Hall, 502 Southtown Cir., Rolesville, NC 27571.