Parker Ridge

Images

** ALL DEVELOPMENT APPLICATIONS WILL BE REVIEWED UNDER THE LAND DEVELOPMENT ORDINANCE (LDO).

Parker Ridge is a proposed residential subdivision comprising up to 162 single-family detached lots and homes, and 114 single-family attached lots (Townhomes) across approximately 88.5 acres. 

ANX 22-06 - Voluntary Annexation Request- APPROVED 03/07/2023 

MA 22-03  - Map Amendment (Rezoning) Request- APPROVED 03/07/2023  

PSP-23-02 - Major Preliminary Subdivision Plat - APPROVED 12/ 22/ 2023 

CID-23-06 - Construction Infrastructure Drawings - APPROVED 12/ 22/ 2023  

CID-23-06 REVISION - Construction Infrastructure Drawings - Approved - TOR 2025-04-20 / Wake Co 2025-04-23 / City of Raleigh 2025-04-24.

SDP-24-10  - Site Development Plan - APPROVED 2025-05-17 TOR / _____ WC / _____ COR - Site Development Plan to develop a part of Open Space 04B, addressed as 506 Cavalera Drive, as an amenity center within the Parker Ridge subdivision.  Four (4) submittals reviewed by TRC Staff between November 2024 and May 2025. 


DORMANT APPLICATIONS

CID-23-07 - Construction Infrastructure Drawings - UNDER REVIEW - Pursuant to MA 22-03 (and PSP-23-02), subdivision infrastructure plans for the off-site improvement to create a driveway at E. Young Street (related to Access D through Town Campus property, see MA 22-03).  V1 Submittal - July-August 2023 / V2 Submittal October-November 2023. 

*Files removed from this webpage 5/17/2025.

CID-23-08 - Construction Infrastructure Drawings  - UNDER REVIEW -Pursuant to MA 22-03. infrastructure plans for an off-site public street (Access D, aka Young Street connector).  V1 Submittal - July-August 2023 / V2 Submittal October-November 2023. 

*Files removed from this webpage 5/17/2025.


UNDER REVIEW

FSP-24-20 - Final Subdivision Plat - Phase 1A - UNDER REVIEW - Final plat to subdivide 19.863  acres and record 55 Single-family Attached (Townhome) lots, being Lot Numbers 1-55, and 4 Open Space lots being HOA Common Lots A, B, C, and Open Space G, and 1408 linear feet of new public right-of-ways (Tree Moss Court, Water Nest Drive), 497 Linear Feet of 24' Public Alley (New Pine Alley), and 500 Linear feet of Variable width Public Alley (New Pine Alley).   Fee-In-Lieu (FIL) due for unbuilt Greenway per CID/PSP approvals.

  • 1st Submittal received 2024-11-01; on TRC-STAFF review during NOVEMBER; comments published on 2024-12-06.
  • 2nd Submittal received 2024-12-23; on TRC-STAFF review during JANUARY; comments published on 2025-02-05.
  • 3rd Submittal received 2025-03-02; on TRC-STAFF review during MARCH; comments published on 2025-03-17.
  • 2025-02-07 - Street Light Poles (8) Fee paid.
  • 2025-03-28 - Bond Estimate for SCM Conversion Surety - Approved.
  • 2025-03-28 - Received Greenway Stub Fee-In-Lieu estimate - requires Approval from Town manager.
  • 2025-04-30 - Bond estimate #3 Approved by Town inspector & engineer.
  • XXX - Parkland Dedication of land under review.

 

FSP-24-24 - Final Subdivision Plat - Phase 1B-S1 (Section 1) - UNDER REVIEW - Final plat to subdivide 67.026 acres and create/record 33 Single-family Detached (SFD) lots , being Lot Numbers 115-133, 180-193 / and 59 Single-family Attached (Townhome) lots, being Lot Numbers 56-114 9 Open Space lots being Open Space Lots #1B (4 different addresses), #4A, #4B (3 different addresses), and #6, and 901 linear feet of 50' public right-of-ways being Granite Knoll Drive, Carved Stone Court / 377 Linear Feet of 60' public right-of-way, Cavalera Way / 1,174 Linear Feet of Variable width Right-of-way, Long Melford Drive.  

  • 1st Submittal received 2024-12-02; on TRC-STAFF review during DECEMBER; comments published on 01-04-2025.
  • WITHDRAWING --> 2nd Submittal received 2025-01-24; on TRC-STAFF review during FEBRUARY; comments to be published by/on 03-10-2025.
  • 2nd Submittal received 2025-03-03; on TRC-STAFF review during MARCH; comments published on 2025-03-21.
  • 3rd Submittal received 2025-04-01; on TRC-STAFF review during APRIL; comments published on 2025-04-25.
    • Street Light pole invoice for 14 Poles issued 2025-04-30 / PAID 2025-05-06.
    • Bond for unbuilt infrastructure requires review/approval by Town engineering/inspector.

 

FSP-25-16 - Final Subdivision Plat - Phase 1B-S2 (Section 2) - UNDER REVIEW - Final plat to subdivide 49.522 acres and create/record 21 Single-family Detached (SFD) lots , being Lot Numbers 134-154 / 1 Open Space lots being Open Space Lots #1C (3.102 ac.) /  987 linear feet of 50' public right-of-ways being Granite Knoll Drive.  The Maximum Impervious Coverage per lot is 2,500 SF.

  • 1st Submittal received 2025-06-01; on TRC-STAFF review during JUNE 2025; comments published on 2025-______.

 

FSP-25-17 - Final Subdivision Plat - Phase 1B-S3 (Section 3) - UNDER REVIEW - Final plat to subdivide 42.797  acres and create/record 43 Single-family Detached (SFD) lots , being Lot Numbers 155-197 / 2 Open Space lots being Open Space Lots #2 (6.204 ac.) and #3 (0.990 ac) /  1,061 linear feet of 60' public right-of-ways being Long Melford Drive; 181 linear feet of 50' public right-of-way being Stone Overlook Court.  The Maximum Impervious Coverage per lot is 2,500 SF.  Per the Lighting Plan there are 8 Street Light poles in this Phase.

  • 1st Submittal received 2025-06-01; on TRC-STAFF review during JUNE 2025; comments published on 2025-______.

Updates

Parker Ridge subdivision - Site Blasting to Begin

May 6, 2024

The civil engineering contractors (Cardinal Civil Contractors) for the Parker Ridge residential subdivision project will commence with ground disturbance including pyrotechnics (ie blasting) beginning May 6th, 2024.  Parker Ridge is located on both sides of Redford Place Drive, east of S. Main Street, generally behind the Food Lion shopping plaza and Rolesville Elementary School and west of the Village at Roleville and Cedar Lakes neighborhoods.  Please direct any questions or concerns to [*UPDATED 12/2024 - Jonathan Massey jonathan.massey@lennar.com or at 984-484-4665 has replaced Garrick Wier garrick.wier@lennar.com] / 786-778-4511 or cdbquestions@civilblasting.com . Notice Letter provided from contractor to nearby residents is uploaded to the Town's project webpage - https://www.rolesvillenc.gov/sites/default/files/uploads/projects/documents/parker-ridge-notice-of-blasting-letter-2024-05-03.pdf .

Parker Ridge Site construction begins

April 8, 2024

On Monday, April 8, 2024, construction site work began for the future residential neighborhood called Parker Ridge, located at 201 Redford Place Drive.   Construction work for the infrastructure of the neighborhood should continue throughout 2024.  UPDATE 12/2024 - Infrastructure Construction is and  will be continueing into 2025. 

Point of Contact for the Developer, LENNAR, is Jonathan Massey jonathan.massey@lennar.com and 984-484-4665. 

Documents

Traffic Impact Analysis (TIA)

MA 22-03 - Planning Board Mtg held 09-26-2022 - Item B.2

Developer Notificiation Letter of Blasting dated 2024-05-03

Wake County GIS/911 Addressing Plan for subdivision

FSP-24-20, Phase 1A - Bond estimate #3 rcvd 04-30-2025

FSP-24-24 - Final Subdivision Plat, Ph 1B - Withdrawn on 02/10/2025

Recorded Covenants/Conditions/Restrictions